schedule iconConstruction of the Harbor Connector Bridge and work along Central Avenue from the bridge to the southern half of the Aliceanna Street intersection began in January 2017. The updated project schedule is as follows.

Milestone Schedule

  • Notice to Proceed

    June 15, 2016
  • Lancaster Street and Central Avenue Closures

    Early January 2017
  • Begin Harbor Point Connector Bridge Construction

    Late January 2017
  • Begin Streetscape Construction

    Spring 2017
  • Harbor Point Connector Bridge Open to Traffic

    Winter 2017
  • Traffic in Final Configuration

    May 1, 2020